Fiord GroupEnvironmental Engineering
Salt-flat salar landscape
Salt-flat salar landscape

Mine water design

Why does a water storage sized at referral stage not fit the approved footprint?

Fiord Group · Hydrology & flood engineering

Mine water design

Because a volume is not a footprint. A storage sized at referral stage is usually sized volumetrically — operating volume plus an allowance for the design storm — and that number is what the clearing figure gets drawn around. The area the finished structure occupies is settled later, by things that only exist once there is a design: the depth the site will permit, the freeboard held above top water level, the spillway with its invert setting and its discharge path, the crest width and the access along it, and the batters that carry the crest down to natural ground. Each is defensible on its own terms. Together they can put the built structure outside the line that was cleared for it. Nothing was wrong with the volume. It was simply the only thing that had been decided.

Volume is a hydrological number; footprint is a geometric one

At referral stage the storage question is usually answered as a water balance. Inflow from dewatering or process return, losses to evaporation and seepage, an allowance for a design rainfall event, and a required operating volume that holds the site through the worst sequence the record supports. That produces a capacity.

A capacity does not have an area until something fixes its depth, and depth is not a hydrological variable. It is set by what can be excavated, what the material will stand up in, how far down the water table sits, and what the site is willing to pump against. Until those are answered the same capacity can occupy very different areas.

The referral figure, though, needs a line on a map. So an area is estimated from the capacity and an assumed depth, and that estimate becomes the cleared footprint. It is the least examined number in the whole package and it is the one that ends up in a condition.

Everything that turns a volume into an area is decided after the referral

Freeboard is the vertical distance held above top water level so that the design event, and any wave run-up, do not carry water over the crest. It is not stored volume. It raises the embankment and, on any sloped batter, it widens the structure at ground level.

The spillway is a structure in its own right, with an invert set at a defined level, an approach, a discharge path and scour protection where the flow returns to ground. The crest carries an access width because the structure has to be inspected and maintained. And the batters that connect crest to natural ground consume plan area in proportion to height — which is why raising an embankment to gain freeboard widens the footprint at the same time.

None of these is an optional refinement. Each will appear in the works approval as a conditioned dimension. All of them are decided after the area has been drawn.

There is no standard freeboard, and the published approvals show it

It is tempting to assume a default figure exists and that a referral-stage estimate can be corrected by applying it later. Reading the instruments does not support that. Freeboard is set per structure, against the design event that structure has to pass and the risk the department attaches to it.

Works approval W6972/2024/1, for hypersaline evaporation ponds at a Western Australian mine site, records overflow spillways located 300 mm above the top of the water level, and a freeboard of 800 mm during time limited operations — a figure that includes a 1% AEP 72-hour rainfall event and a calculated wave run-up distance. The mining proposal for the same infrastructure had been based on a freeboard of 1 m; 800 mm was risk assessed and deemed acceptable when an amendment was granted.

Works approval W6639/2022/1, for evaporation ponds at a Pilbara industrial facility, records a 600 mm freeboard between the maximum operating level and the spillway invert, with 1.1 m total freeboard to the embankment crest, providing capacity for a 1 in 1 000 year AEP 72-hour rainfall event of 619 mm, with an emergency spillway on each pond set at the 600 mm freeboard level.

Two instruments, two different freeboards, two different design events, and in the first case a number that moved between the mining proposal and the amendment. The figure is an output of an assessment, not a constant that can be looked up. Anyone carrying a footprint forward on an assumed freeboard is carrying forward an assumption, and it is worth being explicit that this is what it is.

The spillway is the item nobody counted in area

Of everything on the list, the spillway is the one most often absent from an early footprint, because at referral stage it does not feel like a separate object. It is a line item in a water balance — the route the surplus takes in the event that exceeds the storage.

As built it is an inlet at a set level, a channel or chute of a width determined by the flow it has to convey, and an outlet with protection sized against the velocity arriving at it. That last element sits outside the embankment, downstream, in ground that may not have been cleared at all, because the referral figure was drawn around the pond.

The cascade case is worse again. Where ponds are arranged in series and each is connected to the next by an overflow, the spillways are internal to the system and each one imposes a level relationship on its neighbours. Changing the depth of one cell after the fact is not a local change.

Two disciplines, one structure, and nobody holding the boundary

The reason this recurs is organisational rather than technical. The storage volume comes from a hydrologist during the environmental assessment. The embankment geometry, the fill specification, the liner and the batter stability come from a geotechnical and civil team during detailed design, often a year later and often under a different contract.

Both halves are usually done competently. What is missing is anyone holding the constraint that connects them — that the geometry the second team draws has to close inside the area the first team caused to be cleared. Neither party owns that number. The hydrologist has finished before the batters exist; the civil engineer inherits a footprint as a given and designs to it until it does not work.

This is the same seam the Inland Waters factor opens between hydrology and hydrogeology, and it fails the same way: not through error inside either discipline, but through the absence of a party responsible for the interface.

Why making it deeper is not the free answer it looks like

The obvious response to a footprint that does not fit is to hold the volume and go down instead of out. Sometimes that works. It is worth knowing what it costs on the water side before assuming it.

A deeper, smaller-surface storage evaporates less, which is the point if the objective is to retain water and the opposite of the point if the storage is an evaporation pond doing disposal work. Where evaporative loss is the mechanism carrying surplus water off the site, reducing surface area reduces the disposal rate the whole balance depends on, and the storage requirement rises to compensate. The two changes fight each other.

Depth also costs head. Water has to be lifted out, and where the storage is hypersaline the pumping duty is not a minor operating line. Whether the excavation can stand at the depth proposed is a geotechnical question and not one this practice answers — but the water consequences of going deeper are answerable in advance, and they are usually the ones that decide it.

Where the constraint has to be applied instead

The fix is not a better estimate. It is applying the Part V questions to the water design before the Part IV figure is drawn — resolving the storage to a plan area at top water level, with a stated freeboard, a spillway with an invert level and a discharge path, and an access width, rather than leaving a capacity to be turned into an area by someone else later.

That work is not larger than what is already done at referral stage. It is the same water balance carried two steps further and written down as geometry instead of volume. The difference is that the number on the clearing figure is then a number the structure can actually be built inside.

Which is the unglamorous version of the whole argument. The expensive part of a works approval is rarely the engineering. It is discovering, after the footprint has been conditioned, that the engineering does not fit inside it.

Common questions

Why can freeboard not simply be added to the storage volume?
Because freeboard is not stored volume — it is vertical space deliberately kept empty above top water level so the design event and any wave run-up do not overtop the crest. Adding it raises the embankment, and on a sloped batter a higher embankment is a wider one at natural ground. It increases the plan area of the structure without increasing its capacity.
What sets the surface area of a mine water storage?
Operating volume and design storm inflow set the capacity; depth converts that capacity into an area. Freeboard, the spillway and its discharge path, crest access width and the batters connecting crest to natural ground then add further plan area on top of the wetted footprint. Depth itself is constrained by excavation conditions, the water table and pumping head rather than by hydrology, which is why the same capacity can occupy very different areas.
Is there a standard freeboard for evaporation ponds in Western Australia?
No. It is set per structure in the conditions of the relevant works approval, against the design event that structure must pass. Published instruments differ: works approval W6972/2024/1 records a freeboard of 800 mm including a 1% AEP 72-hour event and calculated wave run-up, with spillways 300 mm above top water level, while works approval W6639/2022/1 records 600 mm to the spillway invert and 1.1 m to the embankment crest against a 1 in 1 000 year AEP 72-hour event. In the first case the figure was also reduced from 1 m by risk assessment on amendment.
Can a storage be made deeper rather than wider?
Sometimes, but it is not free. A deeper storage with less surface area evaporates less, which defeats the purpose where evaporation is the disposal mechanism, and it increases pumping head. Whether the excavation stands up at the proposed depth is a geotechnical question. The water consequences, however, can be resolved in advance and are usually what decides it.
Does an EPA approval fix a footprint or a volume?
Conditions under Part IV commonly fix a spatial extent — the area authorised to be cleared or disturbed — rather than a storage capacity. That is why the mismatch bites in the direction it does: the volume can be revised during design without a further approval, but the area generally cannot. Whether a specific proposal is conditioned on a footprint, a development envelope or something else is determined by the wording of its own Ministerial Statement, and is worth reading before the design assumes it has room.
When should works approval design constraints be applied to a referral?
Before the footprint is drawn on the referral figure. Resolving the storage to a plan area at top water level — with a stated freeboard, a spillway invert and discharge path, and an access width — is the same water balance carried two steps further, and it is what makes the cleared area and the buildable area the same number. Applied afterwards, the same work becomes a reason to reopen an approval.