Fiord GroupEnvironmental Engineering
Open-pit mine site in arid country
Open-pit mine site in arid country

Mining & inland waters

Can you discharge surplus mine water to a creek in Western Australia?

Fiord Group · Hydrology & flood engineering

Mining & inland waters

Not as a first option, and the EPA says so directly. Its stated position is that disposal of excess water to waterways should only be undertaken after other potential uses have been maximised — including mitigating environmental impacts, fit for purpose on-site activities, meeting the demands of other water users, and aquifer reinjection. So the first question a referral has to answer is not whether the receiving creek can carry the flow. It is why the water is going to the creek at all, and that has to be evidenced before the discharge design matters.

The order of preference, in the EPA’s own words

Dewatering is an essential component of many mining operations where mining occurs below the water table, and the EPA says so plainly. What it does not accept is discharge as the default destination for the surplus. The guideline names four things to be maximised first: mitigating environmental impacts, fit for purpose on-site activities, meeting the demands of other water users, and aquifer reinjection.

A submission that opens with the receiving environment and the licence limits has skipped the part that was asked for. The argument the EPA is looking for is the water balance that shows how much surplus is genuinely left once each of those four has been taken as far as it goes. The discharge design is what follows after the number stops shrinking — not the thing that stands in for the analysis.

The impact is the regime, not only the chemistry

The named risk is hydrological before it is chemical. Excess water not used through the mining operation is often discharged to local waterways, which can alter hydrological regimes with consequent changes to ecology and potential destabilisation and erosion of banks. The EPA separately lists, among activities with the potential to impact inland waters, the disposal of mine dewater to surface water systems where this may significantly alter the hydrology of the streams, with consequent impacts to aquatic or riparian ecosystems.

The quality list is worth reading closely as well, because it is not only metals. The EPA names dewatering discharges where the water quality — temperature, heavy metals, carbonates — is a concern. Temperature and carbonate chemistry are the two most often missing from a baseline programme that was scoped around a metals suite, and they are the two hardest to add retrospectively, because the pre-discharge condition they would have been compared against no longer exists.

Why a continuous discharge into an occasional creek is the hard case

The EPA’s definition of a waterway expressly includes systems that flow permanently, for part of the year, or occasionally. A great deal of Western Australian inland drainage is the third kind. A dewatering discharge that runs at a steady rate turns a channel that flowed for days in a year into one that flows every day of it.

Every water quality number in that scenario can sit inside its limit and the hydrological regime has still been changed fundamentally — which is the first half of the environmental objective, not a secondary consideration to it. Riparian vegetation responds to permanent water. Banks shaped by short, high flows behave differently under sustained low ones. The ecology that establishes is not the ecology that was there, and at closure the discharge stops and that new ecology loses its water source.

An assessment that anticipates this describes the regime change and its consequences directly, including what happens when the discharge ceases. One that does not leaves the reviewer to infer it from a compliance table, and the query comes back.

What the evidence has to cover

From the guideline’s information list, applied to a discharge: characterise the receiving system — hydrology, water quality, catchment boundaries, geology and connectivity, locally and regionally; describe how excess water is to be disposed of and how that might impact the environment; characterise the waste generated and the pathways for potential contamination, quantified through models where necessary; and predict the changes to the surface water regime that result.

Then follow the water. The guideline asks for the potential consequences of any hydrological or water quality change on downstream waters such as estuaries or the marine environment — so a discharge assessment that stops at the property boundary has stopped early. It also asks for significance evaluated across direct, indirect and cumulative impacts in a local and regional context, cumulative being the one that catches an operation in a catchment where neighbours are doing the same thing.

And then the arrangements: monitoring, mitigation, management, closure and rehabilitation, the predicted outcome against the environmental objective, whether a significant residual impact is likely, and the adaptive management or contingency planning that applies if the predictions are wrong.

Part IV is not the only approval

An EPA assessment under Part IV of the Environmental Protection Act 1986 is the impact assessment. A discharge from a prescribed premises is separately regulated under Part V, where a works approval is required before construction and a licence or registration is required before an emission or discharge is caused. The two run on different timetables and ask different questions of the same water.

They do draw on the same evidence, though. Receiving-environment characterisation, the water balance and the discharge quality prediction are inputs to both, and building them once to a standard that satisfies the harder reader is cheaper than building them twice to two different ones.

When the work is worth doing

The surplus volume is an output of the mine plan and the dewatering schedule, so it moves whenever those move. Building the surface water case late means building it against a number that is still changing, and the version that reaches the regulator is the one that had the least time.

The unglamorous alternative: a water balance early, receiving-environment baseline started before there is a discharge left to characterise it against, and a discharge case written from a position where the four alternatives were genuinely tested rather than retrospectively justified.

Common questions

Does the EPA allow mine dewater to be discharged to a creek?
It is not prohibited, but it is not the starting point either. The EPA’s stated position is that disposal of excess water to waterways should only be undertaken after other potential uses have been maximised. A referral is expected to show that analysis, not just the design of the discharge that follows it.
What alternatives does the EPA expect to be considered before discharge to a waterway?
Four, named in the Inland Waters guideline: mitigating environmental impacts, fit for purpose on-site activities, meeting the demands of other water users, and aquifer reinjection. The expectation is that each has been maximised before the residual surplus is proposed for discharge.
Is water quality the main issue with a dewatering discharge?
It is half of it. The EPA’s objective covers hydrological regimes and water quality together, and the guideline’s stated concern with discharge to waterways is that it can alter hydrological regimes, with consequent changes to ecology and potential destabilisation and erosion of banks. A discharge that meets every quality limit can still change the flow regime of the receiving system.
Which water quality parameters does the EPA specifically name for dewatering discharges?
The guideline names temperature, heavy metals and carbonates as parameters of concern for dewatering discharges. Temperature in particular is often absent from baseline programmes scoped around a metals suite.
Does a discharge assessment have to consider downstream estuaries?
Yes, where they are within reach of the change. The EPA’s information list asks for the potential consequences of any hydrological or water quality change on downstream waters such as estuaries or the marine environment, and downstream marine ecosystems appear in its list of significant ecosystems.
Do I need a Part V licence as well as an EPA assessment?
They are separate approvals. The EPA assessment sits under Part IV of the Environmental Protection Act 1986. Discharges from prescribed premises are regulated by DWER under Part V, which requires a works approval before construction and a licence or registration before an emission or discharge is caused. Whether Part V applies depends on whether the premises falls within a prescribed category, which is a question worth resolving early rather than at the end.

Sources

Every figure and requirement above is traceable to one of these. Regulatory documents in Western Australia change — where a source has been superseded, the article says so rather than quietly citing the current one.