Detention Basin Assessment
Overview
Construction hardstands built inside a detention basin during a health campus redevelopment took storage out of it. The assessment quantified what that cost the basin, and whether the shortfall could be left in place permanently.
Location
South West, WA
Sector
Infrastructure & Government
Scope
Flood Impact Assessment · Hydraulic Structure Design
Rather than rebuild the hydrology, the earlier validated 2D model was reused with only its basin geometry updated from as-constructed survey — new breaklines, new stage–storage curves, everything else held constant so the before-and-after comparison measured the infill and nothing else.
Temporary works have a way of becoming permanent once the cranes leave. Answering that honestly means re-running the original model on the original assumptions, because a fresh model with fresh inputs cannot tell you how much of the change was the pads and how much was the method.
More in Infrastructure & Government
Next Project
Estate Dam Failure Assessment
Victoria